It is an obligation of the consultant QS to assess the progress claim
submitted by the Contractor during post contract stage. Does he responsible for
any overvaluation due to certifying any defective works?
Below court case outcome will give you some light on the above subject
matter.
The Employer had appointed an Architect under the contract (JCT); the
Architect had employed a QS firm undertake cost management duties including
assessing progress claims. The JCT requires the Architect to certify the value
of work which were "properly executed', therefore by definition, any
defective works shall not be certified by the Architect.
However, wrongly, the QS’s valuation had included some defective works
They also point out the below statement from Sutcliffe v Chippendale
& Edmondson (1971) 18 BLR 149 case.
"the architect … should first satisfy himself as to the acceptable
quality of the work, before requiring his employer by way of certificate to
make payment for it, and in particular should keep the quantity surveyor
continually informed of any defective or improperly executed work which he has observed'.
“if the architect did not tell the quantity surveyor about the defects,
the quantity surveyor would not be expected to make allowance for them…It
was simply for the quantity surveyor to
see what work had been done and, if he
had no evidence to the contrary, he was to assume that the work had been done
properly”
Employer was trying to establish that, with Contrary to the conclusion
of above case, the QS was requiring to inform the architects about defective
works, and he is liable for quality matters at least to the extent that the
defects were "obviously defective'.
However, the court has not found any basis in fact or in law, to allow
the alleged implied duty and therefore, the QS is not responsible for
inspections on quality matters. However, the court found that there was an
implied term, that the QS should act with the reasonable skill and care when
valuing the works.
Author’s note: My opinion is, since QS curriculum(s) are including
learning on defects, they shall responsible for certifying any work with
‘oblivious defects’. I can recall that during our undergraduate studies, we
learned building defects and did a course work on identifying existing defects
in a building and then prepared method statement for rectifications, obtain
quotation from suppliers and presented a full report including the rectification
cost. However, whether a particular defect is an ‘oblivious defects’ or not is
required to decide based on various factors such as extent of the QS
involvement for the valuation and his capability. For an example, an assistant
QS’s may have no knowledge on the building defects but a Senior QS has; if the
QS use to measure work by visiting site may observe any oblivious defects but
not the QS value the work from drawing without going to site(e.g. in Lump sum
contracts). However, if a claimant could be able to demonstrate that a QS had
acted less than ‘reasonable skill and care’, under any circumstance, he may
subject to guilty.
The Case: Dhamija v Sunningdale Joineries Ltd [2010] EWHC 2396 (TCC); [2011]
P.N.L.R. 9; [2010] 10 WLUK 207 (QBD (TCC))