The case covers a few key issues.
Background: This Australian case relates to the issue of a payment schedule. Under the Security of Payment Act, each payment claim shall be replied to by the CA with a payment schedule within a specified period. Also, CA cannot issue one payment schedule for multiple payment claims. If no payment schedule is issued, C is entitled to get paid for the payment claimed (even if there is no entitlement under the contract). CA issued a payment schedule for the payment claims as the payment due is “NIL”. So, the C trying to establish that the additional work they executed is a separate contract rather than variations, so he should be paid as no payment schedule was issued for the additional work/separate contract.
1)Is the
additional work a variation or a separate contract?
1.
Contract- All V to be in writing as directed by
the CA (Superintendent in this case)
2.
Email dated 29 August 2017- From C to CA:
“We have noticed some changes like additional freezer room; therefore, are we to proceed on this basis, or is this subject to variation approval”.
3.
Email dated 30 August 2017- From CA of the E to
C:
“Should this result in a cost or time impost pls submit a
variation which will be processed in the normal manner. Work orders will be
raised on all approved variations. No work to proceed without work
orders.”
The above email is significant due to the following reasons:
·
Work orders will be raised
·
No work to proceed without work orders
·
Issued by the CA(in the contract superintendent)
·
The project was conducted thereafter in
accordance with that direction
·
The director was never revoked
5.
CA issues number of Work Orders
6.
Conclusion- None of the work orders constituted
separate contracts. Each was an approved variation.
““A party may expressly or impliedly give up its right to
insist on a contractual condition. On
the evidence, the referee found that that was what the plaintiff had done. By its
conduct throughout it had waived a right to insist on strict performance of the
conditions of the Contract with respect to the making of claims generally…”
(Hammerschlag J in Corbett Court Pty Ltd v Quasar Constructions (NSW) Pty Ltd
[2008] NSWSC 1163 [110] )
“According to its strict legal connotation, waiver is an
intentional act done with knowledge whereby a person abandons a right by acting
in a matter inconsistent with that right.” (Mason CJ in Commonwealth of
Australia v Verwayen (1990) 107 CLR 394 at [406]-[407] )
2.
Conclusion - E’s conduct in respect of the
approval of the additional work on the contract constituted a waiver of its
right based on the following:
·
The email of 23 February 2018 did not direct the
first respondent to cease all work
·
E intended the C to continue to make enquiries
with respect to the requirements for the roadworks.
How to avoid such issues: Make sure the CA issue V only uses a pre-defined format, not via email, etc. As the QS, always ask for
the V instruction when certifying the payment.
Case: https://archive.sclqld.org.au/qjudgment/2019/QSC19-081.pdf
Note: The article was also published on www.aact.lk
No comments:
Post a Comment
මෙම ලිපියට අදාලව ගැන ඔබ දන්නා වෙනත් කරුණු ඇත්ද?එවාද, විෂයට අදාල ඔනැම කරුණක් මෙහි සටහන් කරන්න.
යුනිකොඩ් එසැණින් පරිවර්ථකය.