Scottish Court Offers Clear Directions on Extension of Time Evaluation

The Appeal Court ratification of the decision in City Inn v Shepherd Construction [2010] provides clear and concise guidelines for evaluating EOT claims. This will be of interest to all quantity surveyors having to deal with EOT claims.

Introduction

The recent case of City Inn v Shepherd Construction has put a ‘damper’ on the reliance by Architects, Engineers and Planners on set rules of critical path analysis and concurrency in their attempts to defeat Contractors’ claims for extensions of time. By far this appears to be first case that has dealt with such issues and advocated a common sense approach to dealing with delays to a construction operation. In the case under discussion, decided Lord Drummond Young, detailed critical path analysis was rejected instead a sensible approach which is more practical in the assessment of delay events was favoured. Also the manner of “apportionment” of delay between the parties where there was no “dominant cause” of delay was also rejected by Lord Drummond Young. This therefore raises a serious question in apportioning delay due to concurrency in the evaluation of extension of time claims from contractors. Perhaps a deeper examination of the facts of the City Inn v Shepherd case might shed some light on these issues.

 The Facts

The disputed between City Inn, the Employer and Shepherd Construction, the Contractor is in respect of delay in completion of a hotel for City Inn in Bristol, England. The contract was based on an amended JCT standard form of building contract (with quantities), 1980. The contractor had been awarded 9 weeks extension of time (4 weeks by the architect and 5 weeks by the adjudicator). The Employer, City Inn disputed the decisions of the architect and adjudicator and challenged these decisions and sought various orders including a declaration of disentitlement of any extension of time. The Contractor Shepherd counterclaimed for 11 weeks extension of time and associated loss and expense.

The evidence produced at the trial indicated that there were qualifying events and also delays caused by the contractor concurrently with some qualifying events which all contributed towards the delay in completion of the project.

The Court of First Instance Decision

The case in the Court of First Instance was heard by Lord Drummond Young who concluded that the task of the decision maker under clause 25 of the contract was to make a “judgment” and, ultimately, arrive at a “fair and reasonable” decision on an extension of time. Where there was concurrency (that is, the relevant event and the contractor risk-event existing at the same time), irrespective of when the events began (or ended), in the absence of one event being “dominant”, achieving a fair and reasonable outcome may involve an apportionment exercise and that the “but for” test of causation did not apply in the context of clause 25. On the basis of this analysis Lord Drummond Young agreed with the architect and adjudicator and held that the contractor was entitled to an extension of time and that the 9 weeks extension of time granted was fair and reasonable.

The employer, City Inn appealed and the appeal was heard by three judges who all rejected City Inn’s appeal and set out five propositions for a proper approach to the application of clause 25 as follows:
  1. Before any claim for an extension of time can succeed, it must be shown that the relevant event is likely to delay or has delayed the works.
  2. Whether the relevant event actually causes delay is “an issue of fact which is to be resolved, not by the application of philosophical principles of causation, but rather by the application of principles of common sense”.
  3. The decision maker can decide the question of causation (that is, whether the event has caused delay to completion) by the use of whatever evidence he considers appropriate. If demonstrated to be sound, this may take the form of a critical path analysis, but the absence of such an analysis does not mean the claim will necessarily fail.
  4. If a dominant cause can be identified in respect of the delay, effect will be given to that by leaving out of account any cause or causes that are not material. If the dominant cause is not a relevant event, the claim will fail.
  5. Where there are two causes operating to cause delay, neither of which is dominant, and only one of which is a relevant event, a contractor’s claim for an extension of time will not necessarily fail. Rather, it is for the decision maker “approaching the issue in a fair and reasonable way, to apportion the delay in completion of the works… as between the relevant event and the other event.”
All three judges agreed that a critical path analysis was not essential to carry out the exercise (although it may be relevant). All three judges also disagreed with HHJ Seymour QC’s comments in Royal Brompton Hospital NHS Trust v Hammond & Others (No 7) 2001 76 Con LR 148 to the effect that a relevant event falls to be disregarded if a pre-existing contractor default would nonetheless have caused delay.

How does this decision affect future claims for extension of time?

Before arriving at any conclusion it is essential to understand the approach of the learned judges all of whom appear to place emphasis on the need for a “fair and reasonable” decision on extensions of time. Lord Osborne expressed dissatisfaction at the various attempts (by architects, engineers and planners) at classification of “concurrent delay” or “concurrent delaying events” when he stated that:

“It may not be of importance to identify whether some delaying event or events was concurrent with another, in any of the possible narrow senses described, but rather to consider the effect upon the completion date of relevant events and events not relevant events. For that reason, discussion of whether or not there is true concurrency, in my opinion, does not assist in the essential process to be followed under clause 25.” 

The Appeal Court decision is also a rejection of the insistence by planners that a critical path analysis is essential to demonstrate an extension of time entitlement. However, the court recognised that there is some value in critical path analysis, but it is for the decision maker to decide if such evidence is of assistance. A claim will not necessarily fail in the absence of such evidence. 

How does the decision maker (architect, engineer or planner) apportion delay in the event of concurrency?

A majority of the court supported Lord Drummond Young’s apportionment exercise in the event of concurrency where no cause is dominant, although Lord Osborne does emphasise that it is “open” to the architect to apportion as part of approaching the issue in a fair and reasonable way; he is not compelled to do so.

In my view this is not the end to the question, the question of concurrency, causation and apportionment will continue to dominate the EOT scene. The Shepherd case is based on the JCT 80 form of contract and does not necessarily apply to other forms where clear statements are contained for dealing with extension of time. It must also be pointed out that the rejection of “critical path” analysis in the Shepherd case should not be taken as a precedent where the production of a programme in such format is the requirement in a contract. In the Shepherd case it was found that it was not possible to accurately recreate the critical path. This therefore certainly does not give any licence for contractors to deviate from any contractual requirement for providing electronically generated programmes in critical path format.

As to the application of concurrency in the apportionment of delay, the decision makers must take into account the event of dominant delay and apply a common sense judgement on arriving at a fair and reasonable conclusion. If the dominant delay is attributable to the employer, then the contractor’s delay will not matter (even if concurrent with the qualifying delay) common sense dictates that the contractor will be entitled for an extension of time because it was the dominant event that caused the eventual delay irrespective of the concurrent delay.

References:


CHOAT, R; “Pulling Out all the stops”- RICS Construction Journal (Nov. – Dec. 2010).   

By. Dr. M. Haris Z Deen

(Many thanks for Dr. Haris Deen for providing us with this valuable article)

Wednesday, 30 January 2019

GUARANTIES AND WARRANTIES QS’S NIGHTMARE OR DILEMMA

I have frequently been asked by Quantity Surveyors and Engineers alike, very senior people as well as students to explain the difference between Guaranties and Warranties. This becomes even more confusing to some when lecturers speak about collateral warranties in respect of construction contracts.

Guaranties and Warranties have immense significance in the interpretation and administration of contracts. Both have the same meaning but in different contexts. In respect of a construction contract this can best be demonstrated by a diagram as follows:



  






The above diagram suggests that the contractor provides a Guaranty to the owner and the sub-contractors and suppliers give guaranties to the contractor respectively while warranties are obtained from manufacturers of plant, materials and goods they supply for incorporation in the works. The ultimate producer of the construction facility is the contractor and he guarantees to the owner that he has constructed the facility to the details and dimensions shown on the drawings and using the materials and workmanship as required by the contract specifications and also that his sub-contractors have done the same. He will also guarantee that the materials that he has procured from his suppliers have been guaranteed by his suppliers as being of the respective kinds as specified in the contract specifications.

A Warranty on the other hand (as far as our discussion is concerned) is a written guaranty given by the manufacturer to the contractor or sub-contractor whoever the purchaser is (through the vendor, the manufacturer’s vendor). This in fact is an agreement assuming responsibility for the proper functioning of the product and that the product is fit for purpose. It is a promise or assurance given in writing that attests to the quality of a product or service or a pledge that something will be performed in a specified manner.

So what is the difference? Most of my students and also practicing quantity surveyors often ask me this question, mainly at the time a project is completed and being taken over.

Defining Guaranty seems simple but if a Warranty is also a guaranty why should it be identified differently? Looking at the diagram I have given above, it would appear that the contractor, by virtue of the contract, guarantees to the owner that he will do whatever he has contracted to do using the specified materials and best workmanship to produce the final end product to the satisfaction of the owner. Similarly, the sub-contractors, by virtue of their contract with the contractor have guaranteed to the contractor that they will likewise deliver their part of the works in the same manner. Insofar as the supplier is concerned, he can guarantee only that the materials, plant and goods supplied by him is of the brand and type ordered by the contractor and at the time he supplied them the manufacturer has warranted (guaranteed in writing) that the materials, plant and goods are of the specification that is written down.

Guaranties provide additional rights which could be a useful back-up in case of a complaint. Therefore, one must make sure that a manufacturer’s guarantee given in the form of a warranty is written in clear and unambiguous terms and bears the vendor’s stamp of authenticity. It is good practice to read the small print contained in a warranty in order to ensure that the product that is being bought is manufactured as specified and meets to owner’s requirements. It is also essential to ensure that the vendor supplies the buyer with the manufacturer’s registration card duly filled for the buyer to return this card to the manufacturer. This will serve as proof of purchase on the date the materials, plant or goods were purchased. This warranty is effective only when the buyer returns the registration card to the manufacturer to the address stated in the card.

For some plant or equipment like air conditioners, chillers, generators, heat exchangers and the like the manufacturers provide warranties extended beyond the normal defects liability period. Besides, even in the case of the normal one year warranty this might extend beyond the defects liability period depending on the date of purchase, or vice versa. This is a serious dilemma for the quantity surveyor who is administering the contract. To whom does he turn to when a breakdown happens?

In the same vein is the legal requirement in most countries for decennial liability guarantees from contractors. In most Middle Eastern countries the contractor and the designer is jointly and severally liable for stated defects including subsidence for ten years from the date of completion. A ten year guarantee of this nature is worthless if the contractor and the designer both go out of business during this period. In the United Kingdom and all European, American and North American countries, this is underwritten by insurance companies, thereby transferring the risk to insurance. In the UK there is the National House Building Council (NHBC) insurance for its members.

While the owner is protected from the contractor’s guarantee by the provisions of the contract for the duration of the defects liability period and any manufacturer’s warranty granted to the contractor during that period, what happens after the contractor is relieved from his obligations on the issue of the final certificate by the owner? As established in the case of Donoghue v Stevenson [1932] All ER Rep 1, the neighbor principle adduced by Lord Atkins will apply and the owner will have no remedy as he has no contract with the supplier. How, therefore can the quantity surveyor advise the owner to overcome this difficulty?

According to the United Kingdom law, liability arises where the defect becomes evident to the consumer within two years of delivery of the goods, unless the defect was or should have been apparent to the consumer at the time of the sale. Any defect apparent within six months of delivery is presumed to have existed at the time of delivery unless proof to the contrary is furnished or this is incompatible with the nature of the goods or the defect. The Sale and Supply of Goods to Consumers Regulation 2002 (UK) requires that when a guaranty is given free of charge with a product, it must be made available in writing and the terms of the guaranty should be set out in plain language which can be easily understood.

But whatever the law says considering the decision in Donoghue v Stevenson cited above, it will not be worth the paper that is written on for the owner, because he did not buy the goods as such he has no contract with the manufacturer and his claim will be too remote thus not meeting the requirements of the neighbor principle.

The difficulty in a construction contract arises when the facility is taken over and the operations and maintenance of the facility is thereafter transferred to the owner’s staff. How can the owner protect himself from a litigious situation arising out of this?

Prior to 1980 owners were able to obtain damages against negligent contractors and consultants through the courts without the need to demonstrate that they had any contractual rights. In fact they have no contractual rights in respect of a third party warranty. This all changed with the 1988 decision in the case of D&F Estates v Church Commissioners in 1988 where it was held that owners and occupiers of buildings needed a contractual remedy in order to pursue claims for certain types of losses. Thus the era of collateral warranties was born.

A collateral warranty is a contract which gives a third party (the owner) collateral to rights in an existing contract entered into by two separate parties (the contractor and the manufacturer or contractor and the sub-contractor or even the contractor and any consultant).  Collateral warranties bring about a concentration of interests between those giving such collateral warranties and those receiving them. It is however not as simple as it sounds. The collateral warranty must be executed as a deed to be effective. The reason being no consideration has passed between the owner and the manufacturer and a contract executed any other way will not be valid. There are several standard forms available. One such form is the one published by the British Property Federation and are designed to limit the warrantor’s obligations.

Collateral warranties must be considered at the very outset of a construction project. It is essential to include in the construction contract and consultants’ appointments the necessary provisions to protect the owner from any adverse effect on the marketability and value of the project.

The owner may require warranties from sub-contractors and consultants, particularly from those with design responsibility. Warranties from the contractor and design consultants are of prime importance. Sometimes it might be required to obtain such warranties from other consultants and sub-contractors alike depending on the extent of their involvement in the project execution.

Whatever the form of warranty selected the words therein must be very carefully formulated to include the correct warranties and the period. Sometimes the warranty underwritten by insurance in which case the terms of the insurance must be meticulously inspected for exclusions or other adverse conditions set by the insurers.

The collateral warranty guarantees a clear right for the owner to take action against the third parties who provide these warranties which he would otherwise be denied.


It would by now be clear that there is no difference between a guaranty and a warranty except that a warranty is a written guaranty.

M. Haris Z Deen
PhD, MBA, BSc., LLB (Hons) FRICS, ACIArb (retd), MAACE

Many thanks for Dr. Haris Z Deen for providing us with this valuable article.

Sunday, 23 December 2018

GOOD NEWS FOR OWNERS SUFFERING FROM DEFECTIVE WORK BY CONTRACTORS




There is some refreshing news for owners suffering from defective construction work by main contractor and sub-contractors – domestic or nominated by a recent decision of the New South Wales (NSW) Australia Court of Appeal – PND Civil Group Pty Ltd v Bastow Civil Construction Pty Ltd [2017] NSWCA 159 (27 June 2017).

The case arose out of a claim for damages by a main contractor, particularly costs incurred by him for rectifying defective works executed by a sub-contractor.

Reading between the lines it might sound simple, but there is more to it than meets the eye. In the context of defective work carried out by a main contractor or any of his sub-contractors, it is the main contractor’s responsibility under any building contract to put it right for the owner with whom he has a contract and from whom he has received payment for the works. Extending this rue or maxim, whatever one might call the sub-contractor has a similar responsibility to the main contractor but not to the owner as the sub-contractor has no contract with the owner and all sub-contract work payments are paid direct by the main contractor from monies he has received from the owner. So, then what seems to be the problem?

When defects are detected either in a punch list at the time of taking over the works from the contractor or latent defects appear during the defects liability period (or defects notification period according to the FIDIC Red Book), the defects have to be rectified at his own by the person who caused – to the owner it is the main contractor, to the main contractor the sub-contractor. That may be simple in terms of understanding, but consider the time and expenses of the owner and his staff and the inconvenience he is put through depending on the extent of the defects.
I have ventured to cite the NSW case stated above in full for the benefit of owners, consultants, and contractors alike who continue to suffer from defective work and not only put stakeholders in difficulties but also many of the construction team’s reputation at stake. Incidentally, NSW and all Australian cases for that matter, being common law cases akin to Sri Lanka decisions of the Australian Courts can be cited in support in Sri Lanka as well as long as the case cited is not remote or overridden by another decision.

This case centers upon whether the one suffering the effects of the defective work can claim the cost of management time as damages.

THE FACTS OF THE CASE

Bastow Civil Constructions (Bastow) contracted with Energy Australia to undertake work that involved constructing trenches in public roads, installing cable ducts in those trenches and backfilling and sealing trenches.

Bastow subcontracted some of that work to PND Civil Group (PND).
Bastow claimed that PND's work was defective and successfully sued PND in the District Court of New South Wales, for (part of) the cost of the rectification works.

The District Court judge concluded that Bastow had suffered loss and quantified Bastow's loss as the costs of the rectification work, namely $269,355.

In quantifying the loss, the District Court judge excluded an amount of $43,669 claimed by Bastow for the time its employees spent in connection with the defects and their rectification.

The $43,669 part of Bastow's claim against PND was rejected by the District Court judge because "there is no evidence that the allocation this time resulted in any additional cost to Bastow".
Bastow challenged this conclusion in its cross-appeal filed in the New South Wales Court of Appeal.
Bastow submitted that the District Court judge had erred in holding that Bastow was not entitled to recover, as an element of its damages, the cost of the management time spent by its employees in dealing with PND's defective work.

THE DECISION OF THE NSW COURT OF APPEAL

The NSW Court of Appeal unanimously found against Bastow concluding that there was no evidence that Bastow had incurred any additional management expenses.

The Court found that:

a. it did not appear that Mr Bastow caused himself or the other staff member involved (who were both employees of Bastow) to be paid overtime or any other compensation or additional remuneration;
b. nor did it appear that any additional staff or contractors were employed, either to
i. to deal with PND's defective work and its consequences, or
ii. to attend to tasks from which Mr Bastow had been distracted because of his attention to matters of defect rectification; or
c. there was no evidence that Bastow had been prevented from seeking or taking up any valuable business opportunity because Mr Bastow's attention was focused on PND's breach of the contract and its consequences.

When might the cost of management time be allowed in a damages claim for rectification of defective work?

To successfully claim the cost of management time, as damages for breach (defective work), the claimant must prove that it incurred additional expense.
The Court noted that damages may be recoverable for lost management time in certain circumstances such as where the Claimant can prove that;
a. existing staff were paid more, or
b. additional staff were employed to either:
i. manage the breach of the contract and its consequences; or
ii. attend to tasks from which existing staff had been distracted because of their attention to the defective work issues; or
c. if no additional staff were employed, but the diversion of management time to the breach of contract meant that the employer lost other valuable business opportunities, then damages might be allowed, although the quantification of lost business opportunity may be difficult to establish.

So how can this decision be good news for the Owner or Main contractor?

Take heart one can still claim damages for the cost of management time lost in dealing with the rectification of defective work carried out by your contractor or subcontractor, but you must prove that you have incurred additional costs.

These additional costs incurred, which you must be able to prove, will most likely be in the form of:
a. additional payments (such as overtime or additional remuneration) made to staff members; or
b. the employment or engagement of additional staff or contractors, either to deal with the subcontractor's defective work and its consequences or to attend to tasks from which your employees have been distracted because of their attention to the rectification of the defective work.

Hence it is not a closed door for you if you are prudent enough to have records as the British eminent contacts and claims lawyer and Quantity Surveyor often stresses in his lectures – RECORDS, RECORDS AND RECORDS and nothing like proper records will prove a claim.

By M Haris Z Deen
Ph.D., MBA., BSc., LLB (Hons)., FRICS

Note: Many thanks to the Dr. Haris Deen for providing us with this article.

Saturday, 19 May 2018

ඉදිකිරිම් නීතියට පෙරවදනක්


1)      නීතිය යනු

නීතිය යනු මානව චර්‍යාවන් නියාමනය උදෙසා පනවා ඇති නියමයන්ය. මානව ක්‍රියාකාරකම් නිසා ලැබුණු අත්දැකිම් නිසාවෙන් පැනවුණු මෙම නියමයන්,  මානවයාගේ උප්පත්තියේ සිට විපත දක්වාත්, ඉන් පසුවත් බලපායි. සමාජයේ හර පද්ධතියක් ලෙසින්ද ක්‍රියාකරන  නීතිය, සමාජයේ සංවර්ධනයට රුකුලක් වන අතරම සමාජයේ සාමාජිකයින් අතර බැදිම ඇති කරයි. විටෙක සමාජයේ යහපත උදෙසා  මානව පැවතුම සිමාකරන අතර   එයට අනුකූල නොවන අයව දඬුවම් කරයි/සමාජයෙන් බැහැර කරයි. 

2)      නීති පද්ධති (legal systems)

ලෝකයේ ඇති නීති පද්ධතින් කිහිපයකි. ඒවායින් ප්‍රධානතම නීති පද්ධතින් දෙක නම් සිවිල් නීති පද්ධතිය (Civil Law system) හා පොදු නීති පද්ධතියයි (Common Law system). රෝම අධිරාජ්‍යයෙන් බිහිවු සිවිල් නීති පද්ධතිය වර්තමානයේ ප්‍රංශය, ජර්මනිය හා මැදපෙරදිග ඇතුළු රටවල ගණනාවක බල පැවැත්වේ. සිවිල් නීති පද්ධතින්හිදි නීතිය ලෙස බලාත්මක කල හැක්කේ, ව්‍යවස්ථාව (Constitution) හා ව්‍යවස්ථාදායකය (legislature, e.g. Parliament) විසින් සම්මත කර ඇති නීතින්ය. පොදු නීතියේ මෙන් අධිකරණයේ නඩු තීන්දු තුලින් නීතින් බිහි නොවේ.
පොදු නීති පද්ධතින්වලදි ව්‍යවස්ථාව හා ව්‍යවස්ථාදායකය විසින් සම්මත කර ඇති නීතින් (උදා: 1995 අංක  11 දරණ බේරුම් කරණය පිලිබදව පනත -Arbitration Act) වලට අමතරව අධිකරණයේ නඩු තීන්දු තුලින් ද නීතින් බිහි වේ (උදා: වේග සිමා ලකුණු කර නැති මාර්ගවලදි අධික වේගයෙන් ගමන් කිරීමේ වරදට දඬුවම් පැමිණිය නො හැක යන්න පසුගිය කාලයේ ලබා දුන් නඩු තීන්දුවකින් බිහිවු නීතියකි ). එනම් නීතින් බිහිවිමේ මුලාශ දෙකකි, අධිකරණය හා ව්‍යවස්ථාදායකය.

3)      පොදු නීති පද්ධතියේ (Common legal system) ප්‍රභේද

පොදු නීතියේ ප්‍රභේද ගණනාවකි, ඒ අතුරින් ප්‍රධානතම දෙක නම්, රාජ්‍ය නීතිය(Public Law) හා පෞද්ගලික නීතියයි (Private Law). පෞද්ගලික නීතිය රටේ පුරවැසියන් අතර ඇති සම්බන්ධකම්වලට බලපාන අතර රාජ්‍ය නීතිය රජය හා එහි පුරවැසියන් අතර ඇති සම්බන්ධතාවට බලපායි. ව්‍යවස්ථා නීතිය (Constitution), පරිපාලන නීතිය (Administrative law), අපරාධ නීතිය (Criminal Law) හා පටිපාටි නීතිය (Procedural Law), රාජ්‍ය නීති සදහා උදාහරණ වන අතර සිවිල් නීතිය (Civil Law), සේවා නියුක්ති නීතිය (Employment Law) හා සමාගමි නීතිය (Company Law), පෞද්ගලික නීති සදහා උදාහරණවේ.
එමෙන්ම හරවත් නීතිය (Substantive Law) හා පටිපාටි නීතිය(Procedural Law) ලෙසින් ද නීතිය වර්ග කරයි. හරවත් නීතිය පාර්ශවයන්ගේ අයිතිවාසිකම් ආරක්ෂා කර දෙන අතර පටිපාටි නීතිය එම  අයිතිවාසිකම් ලබාගැනීමට උපකාර වේ. පටිපාටි නීතියේ ඇත්තේ යම් නඩුවක් ගොනු කිරීමේ හා එයට අදාළ ක්‍රියා පටිපාටියයි (උදා: පාර්ශවයක් අධිකරණයට කැඳවන ආකාරය ). හරවත් නීතියේ ඇත්තේ පාර්ශවයන්ගේ අයිතිවාසිකම්  ලබාගැනීමට අදාළ විධිවිධානයි (උදා: වන්දි ලබාගැනීමේ අයිතිය). සාක්ෂි පනත පටිපාටි නීතිය යටතේ වන අතර ගිවිසුම් නීතිය(Contract law) හරවත් නීතිය  යටතේ වේ.

4)      අපරාධ නීතිය හා සිවිල් නීතිය

සමහර මානවයින්ගේ හැසිරිම තවත් එක් මානවයෙකුට හෝ කිහිපදෙනෙකුට පමණක් බලපාන අතර (පෞද්ගලික හබ) සමහරෙකුගේ හැසිරිම  ඉන් ඔබ්බට ගොස් සමස්ථ සමාජයටම බලපායි(සාමාජයික හබ).
මෙම සමාජයික හබ සමාජයේ පදනමට අහිතකර ලෙස බලපාන බැවින් එම සමාජ විරෝධි ක්‍රියා 'සාපරාධී 'ක්‍රියා ලෙස සැලකෙන අතර ඒවා නීතිය 'අපරාධ' නීතිය (Criminal Law) යටතට ගැනේ. පෞද්ගලික හබ අයත් වන්නේ 'සිවිල්' නීතිය(Civil Law) යටතටයි. අපරාධ නීතිය යටතේ නඩු ගොනු කරනු ලබන්නේ රජය(පොලිසිය) විසින් වන අතර සිවිල් නීතිය යටතේ නඩු ගොනු කරනු ලබන්නේ අගතියට පත් පුද්ගලයා විසිනමය. ශ්‍රී ලංකාවේ නම් මහේස්ත්‍රාත් අධිකරණයේ (Magistrate Court) විභාග කරන්නේ අපරාධ නීතිය යටතේ ගොනු කෙරෙන නඩු වන අතර ප්‍රාථමික අධිකරණයේ (Primary Court) විභාග කරන්නේ සිවිල් නීතිය යටතේ ගොනු කෙරෙන නඩුය. එහෙත් උපරිම අධිකරණයන් වන, අභියාචනාධිකරණය (Appeal Court) හා ශ්‍රේෂ්ඨාධිකරණයේ (Supreme Court) මෙම වර්ග දෙකේ ම නඩු විභාග කරයි. අපරාධ නීතිය යටතේදි අධිකරණයෙන් වරද කරුට දඬුවම් ලබා දෙන අතර (උදා: සිර ගත කිරිම), සිවිල් නීතිය යටතේදි අධිකරණයෙන් අගතියට පත් පාර්ශවයට ප්‍රතිකර්ම කරයි (උදා: වන්දි ගෙවිම ). සිවිල් නීතිය යටතේ එන ප්‍රධානතම අංශ දෙක නම් කොන්ත්‍රාත් නීතිය (Contract Law) හා දිලික්ත/ තෝරත නීතියයි (Tort).

5)      කොන්ත්රාත් නීතිය (Contract law)

ගිවිසුමක්(Agreement) යනු නීතියෙන් බලාත්මක (Enforce) කල හැකි පොරොන්දුවක් (promise) හෝ පොරොන්දු මාලාවකි. මෙසේ ගිවිසුම් පිලියල කිරීමට හා ඒවා බලාත්මක කිරීමට අදාළ නීතිය කොන්ත්‍රත් නීතියයි(Contract Law).
උදා: ගිවිසුමක් නීතිය ඉදිරියේ බලාත්මක කිරීමට නම් එහි, අර්පණයක්(Offer), ප්‍රතිග්‍රහණයක්(Acceptance), ප්‍රතිෂ්ඨාවක්(Consideration), නෛතික චේතනාව(Legal intention) හා ගිවිසුම් ශක්නුතාවය (Capacity) යන මූලිකාංග තිබිය යුතුයි.

6)      දිලීක්ත/ තෝරත නීතිය (Law of Tort)

හානි පුර් ණයට අදාළ නීතිය දිලීක්ත(Delict) /තෝරත(Tort) නීතියයි. දිලික්ත නීතිය රෝම ලන්දේසි නීති (Roman Dutch law) ක්‍රමයෙන් වර්ධනයවු නීතියක් වන අතර එයට අනුරුප ඉංග්‍රිසි නීතිය (English Law) තෝරත නීතියයි. ලංකාවේ ප්‍රධාන වශයෙන් භාවිතා වන්නේ දිලික්ත නීතිය වුවද එයට තෝරත නීතිය බලපා ඇත.
උදාහරණයක් ලෙස වාස්තුවිද්‍යාඥයාගේ සැලසුමේ වරදකින් සේවා යෝජකයාට යම් අලාභයක් වුවහොත් එම අලාභය/හානිය දිලික්ත නීතිය යටතේ එන නොසැලකිල්ල (Negligence)  නිසාවු හානියක් ලෙස සලකන අතර, එය දිලික්ත නීතිය යටතේ අයකර ගත හැකි වේ.

7)      ඉදිකිරීම් නීතිය (Construction Law)

ඉදිකිරීම් නීතිය යනු ඉහත කතා කල ආකාරයේ නීතියේ එක් ප්‍රභේදයක් ලෙස නො සැලකේ. එය ඉදිකිරීම් ක්ෂේත්‍රයට සෘජුවම සම්බන්ධ හා එයට බලපාන නීති ප්‍රබේදයන්ගේ එකතුවකි. කොන්ත්‍රත් නීතිය, දිලික්ත නීතිය, ගැටුම් නිරාකරණයට සම්බන්ධ නීති, ගොඩනැගිලි සැලසුම්කරණයට හා අනුමැතියට අදාල නීති, සේවා නියුක්තියට අදාල නීති, දේපල සම්බන්ධ නීති එහි ප්‍රධාන පාර්ශව වේ. එහෙත් එහි සිමාවක් හෝ ඉදිකිරීම් නීතිය යන්නට එක් නිශ්චිත අර්ථකතනයක් නැත.